NECO Building Construction 2022 Objective and Theory Update

Filed in Exam, NECO News by on February 17, 2022

– NECO Building Construction –

NECO Building Construction Questions are out now on our website. In this article, I will show you past NECO Building Construction random repeated questions for free.

NECO Building Construction 2022 Objective and Theory Update

About NECO

The establishment of the National Examinations Council (NECO) in April 1999 is a culmination of the reaction of the Federal Government.

This was too widespread escalating agitations for a national examination outfit that would respond to the Nigerian needs and demands.

As well as cope with the annually increasing number of secondary school candidates to take Senior School Certificate Examination (SSCE) nationwide.

A Series of panels had earlier been set up to address the issues before this vital decision was taken.

The Mission

To deliver examinations whose results are trusted worldwide for their credibility.

The Vision

To become a major player in the global assessment industry.

Core Value

Redefining the future of the Nigerian child through quality assessment.

The National Examinations Council (also known as NECO) is an examination body in Nigeria that conducts the Senior Secondary Certificate Examination and the General Certificate in Education in June/July and December/January, respectively.

READ ALSO!!!

NECO Result Checker

Buy NECO Scratch Card Online

 All UNN Prospective Students on NECO Results

NECO Building Construction Question and Answers

Question 1

(a) State one duty of each of the following constructional personnel:

Architect;

Quantity surveyor;

Building Inspector.

(b) Sketch each of the following bricklayer’s tools:

Spirit level;

Wooden float.

(c) State three activities involved in site clearing

Question 2

(a) State one use of each of the following building drawings:

site plan;

sectional drawing.

(b) Sketch to illustrate a method of supporting the sides of a trench in firm soil and label the following parts:

poling board;

folding wedges.

(c) State three functions of each of the following elements in a suspended timber ground floor:

air brick;

sleeper wall;

oversite concrete.

Question 3

(a) List three methods of transporting fresh concrete from the ground to the upper floor.

(b) Sketch a straight flight timber stair and label the following parts:

(i) string;

(ii) newel post;

(iii) riser;

(iv) baluster.

(c) List three materials used for the construction of a window sill.

Question 4

(a) State three functional requirements of a roof.

(b) Use a sketch to illustrate the method of fastening a roof rafter to the ring beam.

(c) List three materials used for the manufacture of drain pipes.

Question 5

(a) State two activities involved in landscaping work.

(b) List three materials used for pavement construction.

(c) State two reasons for the construction of kerbs on access roads.

(d) State two reasons for using a metal fence wall gate instead of a wooden gate.

DISCLAIMER! These are not real NECO Building Construction Questions, but likely repeated questions over the years to help candidates understand the nature of their examinations. Ensure to note every question provided on this page.

If you need us to help you with updated questions and answers at the right time about NECO Building Construction Questions, kindly provide us with your phone number and email address in the comment box below.

Also, feel free to ask any questions pertaining to this guide.

What’s your take on this? We believe this article was interesting right. If yes, use our share button below to inform – friends and relations via Facebook and Twitter.

CSN Team.

Comments (2)

Trackback URL | Comments RSS Feed

  1. EMROY says:

    Pls sir will technical drawing be available?

Hey Hi

Don't miss this opportunity

Enter Your Details